A data center planning graphic compares H100/H200 server capacity, contracts, availability, and delivery across London, Crawley, and Cardiff.
UK buyers shopping for H100 or H200 capacity face a harder question than "who is cheapest per hour?" They need to know who can contractually deliver GPUs in Britain for the dates the job runs. The published rates are only partly comparable across AWS, Azure and CoreWeave, and the gaps matter as much as the numbers.

A data center planning graphic compares H100/H200 server capacity, contracts, availability, and delivery across London, Crawley, and Cardiff. What is actually published​

AWS is the only one of the three with a clear London price for eight-GPU H100 and H200 nodes. These are Capacity Block rates, not on-demand rates.

  • A p5.48xlarge (8 × H100) in Europe (London) is listed at $47.757 per instance-hour.
  • A p5e.48xlarge (8 × H200) in London is listed at $54.924 per instance-hour.
  • Independent coverage of AWS's table lists the $47.757 p5.48xlarge rate as covering London and several other regions, at $5.970 per H100.
  • That coverage also stresses that these are reservation rates, not on-demand prices, so they cannot be used as a straight cross-provider comparison.

Capacity Block billing works differently from ordinary cloud billing. Pricing consists of a reservation fee and an operating system fee. AWS's own pricing page says reservation prices are updated regularly based on supply and demand.

In practice, the fee is charged upfront. The prevailing rate at purchase applies even if the block starts later. The next scheduled update is listed as January 2027.

Azure documents the hardware, but the material reviewed gives no UK South price or allocation.

  • Independent tracking of AWS's reservation table offers nothing for Azure, so there is no like-for-like figure to quote.
  • The ND H100 v5 documentation describes a VM with eight 80 GB H100 GPUs. It specifies 3.2 Tbps of interconnect bandwidth per VM and a dedicated 400 Gbps InfiniBand link per GPU. Microsoft's page was last updated 25 September 2026.
  • The NC A100 v4 series offers one to four PCIe A100s with 80 GB each. Its page carries a caution that Microsoft is currently deploying net-new capacity only for the NCads H100 v5 series. That is a useful warning for anyone planning around A100 availability.
  • Microsoft's regions list shows UK South with three availability zones, a physical location of London, and UK West (Cardiff) as its pair. That confirms the region exists. It does not confirm that a given GPU size is deployable there.

CoreWeave has confirmed UK H200 infrastructure, but its catalogue prices are not UK quotes.

  • A 13 January 2025 announcement said two UK data centres, in Crawley and London Docklands, were operational. They run NVIDIA H200 GPUs with Quantum-2 InfiniBand.
  • Crawley went live in October 2024 with Digital Realty, and London Docklands followed in December 2024 with Global Switch.
  • Its public catalogue lists an eight-GPU H200 at $50.44 per hour on-demand, an eight-GPU H100 at $49.24, and an eight-GPU L40S at $18.00.
  • The catalogue does not tie those prices to a UK site. Treat them as screening figures, not quotes for Crawley or Docklands.

Comparison at a glance​

ProviderConfigurationPublished figureUK status
AWS Londonp5.48xlarge, 8 × H100 80 GB$47.757/hr Capacity BlockLondon rate published
AWS Londonp5e.48xlarge, 8 × H200 141 GB$54.924/hr Capacity BlockLondon rate published
AzureND H100 v5, 8 × H100 80 GBNo UK South price verifiedRegion exists; allocation unconfirmed
AzureNC A100 v4, 1–4 × A100 80 GBNo UK South price verifiedNet-new capacity goes to NCads H100 v5
CoreWeave8 × H200 141 GB$50.44/hr catalogue on-demandUK sites announced; UK price undisclosed
CoreWeave8 × L40S 48 GB$18.00/hr catalogueUK availability unconfirmed

The sterling figures quoted in the source (about £36.43 and £41.90 for AWS) rest on an exchange rate of £0.7628 per dollar. I could not confirm that rate for 26 November from the Bank of England data retrieved, so treat the dollar figures as the firm ones.

A word of caution on AWS pricing history​

Other trackers describe AWS Capacity Block rates as moving a lot in 2026.

  • One analysis said an October 7 revision moved P5 to $5.970 per H100-hour, putting an 8-GPU p5.48xlarge at about $47.76.
  • The same analysis noted that several European regions had previously been listed at $4.720 per H100, below US rates.

Older figures you may see elsewhere, such as roughly $41.53 per p5.48xlarge hour, belong to earlier pricing. Check the date on any price you are given.

Also keep the product types separate. On-demand p5.48xlarge prices (for example, about $71.55 in London on one third-party tracker) are a different commercial model from a time-boxed reservation.

Hardware parity is not performance parity​

On paper, AWS P5 and Azure ND H100 v5 are close: both have eight 80 GB H100s and roughly 3.2 Tbps of fabric. AWS lists up to 3,200 Gbps of EFA networking and NVSwitch interconnect within the node. These are vendor specifications, not benchmarks. Real training time depends on the software stack, the collective-communication behaviour and checkpointing. Nothing reviewed supports saying one is faster.

Memory is the practical differentiator:

  • H100 nodes give 80 GB per GPU.
  • H200 nodes on AWS P5e and CoreWeave give 141 GB per GPU.
  • Moving A100 workloads from AWS P4d (40 GB per GPU, per the source) to Azure NC A100 v4 (80 GB) changes your memory headroom.

How to run a fair bake-off​

  1. Ask every bidder to quote the same GPU count, UK site, delivery window and run length.
  2. Get the exact SKU, region and start date in writing. Subscription quota is not physical capacity, and an Azure reservation discount does not guarantee deployment.
  3. Benchmark a representative job at the node count you plan to buy. Hold the model, precision, sequence length, batch size and checkpoint cadence constant.
  4. Record time to target quality, billed node-hours and restart time after a worker failure.
  5. For inference, measure cost per million output tokens at a fixed tail-latency target and request mix.
  6. Itemise storage, networking, support and idle committed hours. An hourly GPU rate is not the whole bill.

A quick worked example from the source: one p5.48xlarge for 24 billed hours at $47.757 comes to about $1,146 for the reservation alone, before storage, networking or other charges.

Data residency is a separate checkpoint​

A UK data centre location does not settle compliance on its own. The source points to the NCSC's cloud security guidance on physical location, legal jurisdiction and logs. It also points to the ICO's view that making personal data accessible to a separate overseas organisation can trigger restricted-transfer rules in some circumstances. I did not verify those documents independently, so check them directly. Map checkpoints, backups, telemetry and support access, not just the live dataset.

Bottom line​

  • Scheduled eight-H100 training: AWS London is the only option here with a published UK reservation rate, so it is the natural first quote to request.
  • Memory-hungry jobs: request matching H200 bids from AWS and CoreWeave for identical dates.
  • Azure-centred estates: shortlist Azure UK South only once Microsoft confirms the VM size, node count and start date.
  • Inference pilots: the source suggests AWS G5 and CoreWeave L40S as candidates. I could not verify UK availability or pricing for either.

The winner is whichever provider can deliver the UK capacity under contract at the lowest total cost per completed run. Headline hourly rates will not tell you that.

 

References

  1. UK Enterprise GPU Cloud: AWS, Azure and CoreWeave Costs - JournalArta JournalArta 2026-11-28T06:45:00+00:00
  2. ND-H100-v5 size series - Azure Virtual Machines | Microsoft Learn learn.microsoft.com
  3. Two Data Centers In The UK Now Operational | CoreWeave coreweave.com